Updated Construction Timeline for Broad Street

The City of Augusta Engineering Department and project contractors are sharing an updated construction schedule for the Broad Street Improvement Project. While work continues to move steadily forward across all downtown zones, recent subsurface findings have necessitated a minor tactical adjustment to our targeted timeline.

During recent excavation phases, crews encountered unforeseen aging pipe infrastructure that required immediate replacement before surface improvements could safely proceed. Addressing these utility vulnerabilities now ensures that the longevity of the Broad Street transformation is protected and avoids disruptive future maintenance. Despite this slight delay, overall progress is moving forward strongly, with additional manpower and coordinated shifts keeping the core streetscape delivery firmly on track.

Progress Spotlight: The James Brown Linear Park (JBLP) is officially taking shape! Passersby will note that new structural foundations and features celebrating the Godfather of Soul are actively being installed, bringing a vibrant cultural centerpiece to life in the heart of the corridor.

Project Schedule: The following schedule outlines the updated active construction windows through completion. We remain tightly structured around performance and performance-driven milestones to restore full, vibrant potential to Broad Street as quickly and efficiently as possible.

SegmentBegin DateEnd Date
13th to 12th04/01/2608/14/26
12th to 11th05/20/2609/03/26
11th to 10th07/07/2609/23/26
10th to 9th07/25/2611/19/26
8th to 7th08/27/2611/06/26
9th to 8th (JBLP)10/15/2612/15/26
7th to 6th08/11/2610/22/26
6th to 5th07/24/2610/05/26
5th to Seg III12/16/2602/25/27

What This Means for You

  • Continued Local Access: Sidewalk access to all local shops, hotels and restaurants remains completely open. Please continue to support Broad Street businesses during this transformation.
  • Traffic & Parking Management: While specific travel lanes or median parking areas may face temporary restrictions during their active segment windows, outside lanes will remain clear to maintain traffic flow.

We deeply appreciate the patience and cooperation shown by our local businesses, residents, and visitors as we safely build a more beautiful, pedestrian-friendly, and economically vibrant Broad Street.The City of Augusta Engineering Department and project contractors are sharing an updated construction schedule for the Broad Street Improvement Project. While work continues to move steadily forward across all downtown zones, recent subsurface findings have necessitated a minor tactical adjustment to our targeted timeline.