The New Pace of Progress: Finalized Construction Timeline for Broad Street

We are pleased to share the finalized construction schedule for the Broad Street Improvement Project. Following the City commission approval of a Change Order to accelerate this work, the City of Augusta Engineering Department and the project contractor have met to agree upon this updated timeline.

This plan is designed to significantly speed up construction between 5th and 13th Streets. By deploying additional crews and resources immediately, the City is ensuring that the most disruptive work in the heart of downtown is finished by the end of 2026. This schedule represents a major commitment to return Broad Street to its full, vibrant potential as quickly as possible.

Project Timeline: Segment by Segment

The following schedule outlines the active construction windows through the completion of this phase. While we are committed to this pace, please note that dates may change. Factors such as weather conditions or unexpected site findings could result in delays or even further acceleration of certain segments. We will keep stakeholders posted in the event that any significant changes occur.

SegmentBeginEnd
13th to 12thApril 16, 2026July 1, 2026
12th to 11thMay 6, 2026July 22, 2026
11th to 10thMay 27, 2026August 10, 2026
10th to 9thAugust 12, 2026October 7, 2026
8th to 7thJuly 31, 2026October 9, 2026
9th to 8th (James Brown Linear Park)August 31, 2026October 27, 2026
8th to 7th (inside lanes)
8th to 7th (outside lanes)
April 16, 2026
July 31, 2026
July 1, 2026
October 9, 2026
7th to 6th (inside lanes)
7th to 6th (outside lanes)
June 1, 2026
July 16, 2026
August 1, 2026
September 22, 2026
6th to 5thJune 26, 2026September 3, 2026
5th to Segment IIIOctober 28, 2026December 15, 2026

What This Means for You

  • Minimized Long Term Disruption: By overlapping work phases and doubling down on manpower now, we are clearing heavy machinery from the downtown corridor much sooner than previously anticipated.
  • Prioritizing Local Business: This finalized schedule was built with our local economy in mind. Our goal is to restore full, easy access to Broad Street shops and restaurants as efficiently as possible.
  • Accountability: The agreement remains performance structured. Additional payments are only issued as these specific milestones are met.

We appreciate the patience you have shown throughout this process. We will keep you updated as we pick up the pace on Broad Street.

Big changes. Bold future. All on Broad.