5th Street: Continued Work By Block

5th Street between Broad Street and Reynolds Street will continue to be closed to through traffic for the next few weeks as work continues to add new curb & gutter, driveways, and sidewalks. Detour is in place.

Expect lane closures along 5th Street between Gordon Hwy and Walton Way as shoulder work begin in this area.

5th Street Update: Shoulder Work In Progress

More shoulder will occur within the next two weeks including concrete removal. Expect continued closure of 5th Street between Broad St. and Reynolds St. Also expect moving outside lane closures along 5th St. between Broad St. and Greene St.

5th Street Update: Shoulder Work Continues

Demolition and construction work continues along 5th Street between Walton Way and Greene Street. Demolition work also continues along 5th Street between Reynolds Street and Broad Street. Expect roaming outside lane closures along 5th Street. Expect a street closure between Reynolds and Broad with detour in the next couple of weeks.

5th Street Update: Continued Demo

Demolition of concrete and electrical will continue along the shoulder of the road throughout the next two weeks. Expect roaming outside lane closures along 5th Street between Walton Way and Greene Street in both directions. Warning signs will be in place for each closure.

5th Street Update: Shoulder Work

Clearing and landscape removal should be completed this week. Asphalt sawcutting will begin this week. Demolition of existing infrastructure will begin within the next two weeks. Expect temporary single lane closures along 5th St. between Walton Way and Greene St. throughout the day.

5th Street Update: 5/9/2023

5th Street will be closed between Broad St. and Reynolds St. starting Thursday, May 11, 2023, through Friday, May 12, 2023. Clearing and tree removal will be taking place. A detour will be in place for the duration of the work. Traffic should return to normal on Saturday, May 12, 2023.

5th Street Update: 5/3/2023

Clearing and grubbing has started along this street. Old street light poles and landscaping are being removed between Telfair Street and Walton Way. Expect traffic to be interrupted along 5th Street with lane closures and detours for the next two weeks.

Atlanta Gas Light will begin relocating utility lines along 5th Street between Walton Way and Walker Street. Expect traffic to be interrupted along 5th Street with lanes closures for the next two weeks.