Broad Street Improvement Project Updates Schedule While Maintaining 2026 Completion for Business Corridor
The City of Augusta Engineering Department and project contractors have released an updated construction schedule for the Broad Street Improvement Project as work continues to advance throughout downtown Augusta. With multiple construction zones now active simultaneously, crews are making steady progress on utility upgrades, streetscape enhancements and infrastructure improvements designed to create a safer, more accessible and vibrant corridor for residents, businesses and visitors.
As construction enters several new phases, project teams have refined the sequencing of work activities to maintain momentum and improve overall efficiency across the corridor. The updated timeline reflects current construction conditions and provides the most accurate schedule for work extending through project completion.
Project Schedule: The following schedule outlines the anticipated construction windows for each segment of Broad Street. These dates are subject to adjustment as crews respond to field conditions, weather, and ongoing coordination efforts, but remain focused on delivering long-term improvements with as little disruption as possible.
| Segment | Begin Date | End Date |
| 13th to 12th | 04/01/26 | 09/14/26 |
| 12th to 11th | 05/20/26 | 10/12/26 |
| 11th to 10th | 08/11/26 | 10/26/26 |
| 10th to 9th | 08/14/26 | 11/19/26 |
| 8th to 7th | 08/27/26 | 10/12/26 |
| 9th to 8th (JBLP) | 08/20/26 | 12/18/26 |
| 7th to 6th | 09/03/26 | 10/21/26 |
| 6th to 5th | 09/10/26 | 10/30/26 |
| 5th to Seg III | 12/16/26 | 02/25/27 |
The City of Augusta appreciates the continued patience, flexibility, and support of downtown businesses, property owners, residents, and visitors as this transformational project moves forward. Once complete, the Broad Street Improvement Project will deliver enhanced mobility, improved infrastructure, expanded accessibility, and a more welcoming downtown experience for the entire community.