13th Street Update: Shoulder and Canal Work Continues

There was a delay in the specialty contractor arriving to do the canal work on 13th Street at Telfair Street. 13th Street between Telfair Street and the Augusta Canal will remain closed into 2024 through the winter. The street should open to full traffic prior to the 2024 Masters Tournament. Expect outside lane closures along 13th Street between the canal and Walton Way for the next few months. Shoulder work and demolition will continue along 13th Street between Broad Street and Telfair Street into winter 2024.

6th Street Update: Lane Work Continues

Expect shoulder work to continue along 6th Street between Greene Street and Fenwick Street. Single lane shifts will take place between Telfair and Fenwick after the holidays into January 2024. Detours will be in place for the lane closures.

5th Street Update: Outside Road Work Continues

Outside lane closures will continue between Broad Street and Walton Way. Street will remain closed between Broad Street and Reynolds Street through the rest of 2023 and into 2024. Expect single lane shifts along 5th Street between Ellis Street and Broad Street the first part of 2024.

Greene Street Update: Old Towne Work Continues

Work continues along the outside Greene Street. Expect outside lane closures on both sides of Greene Street between 5th Street and East Boundary. Drainage work will begin Monday, November 27th in the block near Heritage Academy (3rd Street to 4th Street). During the drainage work, this block of Greene Street will be closed and a detour will be in place. Expect traffic delays in this area.

13th Street Update: Project Construction Extends Beyond Telfair Street

13th Street near Telfair Street will remain closed and a detour is in place. The street closure has been extended until February 2024 due to the availability of the specialty contractor and materials. On 13th Street between Telfair Street and Broad Street, the outside lanes will be closed for shoulder infrastructure demolition. Expect heavy traffic delays along this portion of 13th Street through the spring of 2024.

5th Street Update: Outside Lane Work

The outside lanes of 5th Street between Greene Street and Walton Way will remain closed as crews continue to demolish outside road infrastructure and prepare utilities for the upcoming improvements. Side streets off of 5th Street in this stretch of roadway may be closed for utility work. Detours will be installed where necessary. Expect slow traffic and delays along this portion of 5th Street. 5th Street between Reynolds St. and Broad St. will also remain closed while work continues along this block.

6th Street Update: Continuing Shoulder Work

6th Street between Walton Way and Greene will have lane closures in place for the next few weeks. Expect detours when one side or the other of this street is closed.